30" EAS-36-002 looking W from mixing tank location.
Clmap on 8" WFP-47-100 E-W run next to thrust block at SW corner of campsite.
Chlorination retention tank being lowered into place. Looking SE.
Pit run stockpile - looking W.
14" FRP EA line - looking North from MH #24.
EAS mixing tank - location looking North.
Blowout at or near tie-in for 8" WFP-47-100 at SE corner of camp.
Effluent discharge.
Looking down on break in WFP line near 8" WFP-47-100 tie-in at SE corner of camp looking NE.
View from H.A. Simons field office window.
Looking E. along trench for 24" WMC-36-141. 36" WMC-36-140 & 10" GF-36-120.
Looking East along trench between Power Group & Recaust.
Winter bridge across Fraser River.
See drawing attached [man standing beside railroad tracks]
Drawing attached [railroad plans]
Trench for 24" WMC-36-141, 24" WMC-36-061 & 10" GF-36-204 at E. end looking West.
Power to pulp utility bridge East end - looking West
From just West of #2 seal tank - looking South btween #1 Blow Tank & Digester Tw.
Looking NE from just South of mens locker room.
Looking North between #1 Blow Tank & Digester Tower.
Tank overflow - Bleach plant.
Floor trench overflow - Bleach plant.
Existing acid effluent (EA) from seal tank #15 and Bleach plant looking SW.
Existing acid effluent (EA) from seal tank #15 and Bleach plant looking SW.
Temporary support for chip conveyor bent # looking SE.
Southwest corner of chemical unloading shed looking SE.
"B" mill Pulp Gr. from roof of #1 WWS tank looking NW.
"B" mill Power Gr. from SE. corner looking NW.
"B" mill machinery room from roof of blending tank looking N.
"B" mill machinery room from roof of bleached H.D. tank looking N.
"B" mill MR from roof of bleached H.D. tank.
Condition of pipe under Polykin tape.
Condition of pipe under Polykin tape.
Condition of pipe under Polykin.
MR floor.
1.5" tie in GF#6.
Room roof of Bleached H.D. tank looking N.
Retaining wall at fuel oil day tank looking N.
Precipitation bldg. excavation from NW corner looking SE.
Kiln foundation excavation S. end looking N.
Lime rock track pit from roof of chip surge bin bldg looking N.
"B" mill recovery boiler precipitator foundation excavation from near track #14 looking NW.
Excavation for foundation for new liquor spill collecting tank from NE corner looking SW.
Applying insulation on existing weak B.L. tank.
Lime rock track pit from W. end looking E.
Pouring fndn for tanks along E. wall of "B" mill Pulping Gr. from S. end looking N.
Demolished retaining wall at "A" mill Pulping Gr. knot chute E. end looking NW.
S. end of "B" mill machine room from S. end looking N.
"B" mill machine room broke pit from roof of "A" mill machine room looking W.
Excavation for new B.L. tanks and "B" mill evaporator bldg. from roof of existing warehouse looking S.