Photograph depicts building materials in framework room. Corresponding note on accompanying photo description page: "Pictures taken July 5th, 1952. 10. Mill. Second floor. Looking south."
Photograph depicts buildings in plant site, mountains in background. Corresponding note on accompanying photo description page: "Pictures taken July 5th, 1952. 12. Mill, Power House & Water Tank."
Photograph depicts power house under construction. Temporary camp, service garage, and mountains in background. It is believed that this photograph was taken from top of the plant water tower.
Photograph depicts mill in distance, mountains in background, rocks in foreground. Corresponding note on accompanying photo description page: "Pictures taken June 11th: (1) Erecting timber in mill construction. Tractor in foreground. Looking west."
Photograph depicts men on mill scaffolding, mountains in background. Corresponding note on accompanying photo description page: "Pictures taken June 11th: (4) Mill construction. Looking north."
Corresponding note on accompanying photo description page: "Pictures taken June 11th: (5) Drilling big boulders in truck dump excavation. Looking north."
Photograph depicts mill framework in distance, mountains in background. Corresponding note on accompanying photo description page: "Pictures taken June 28th, 1952: (6) Mill construction. Looking west."
Photograph depicts foundations and framework from interior of building. Corresponding note on accompanying photo description page: "Pictures taken June 28th, 1952: (10) Dryer foundations in mill."
Photograph depicts 9 men working on building speculated to be foundation for diesel engine. (See also items 2000.1.1.2.216 and 2000.1.1.2.217).
Photograph depicts two men working on early stages of building believed to be mill.
Photograph depicts building project and materials in dirt area, mountains in background. Corresponding note on accompanying photo description page: "6: Pouring concrete for second Ruston diesel engine. Mill in background. Looking south." (Note speculated to be incorrect.)
Photograph depicts a long one-story building in airport yard at Watson Lake. Corresponding note on accompanying photo description page: "1. Warehouse, containing refrigerator in the far end and heating plant in the near end. Locked and in good condition."
Photograph depicts mill in early stages of construction, trees in foreground, mountains in background. Corresponding note on accompanying photo description page: "11. Erecting wall post on mill foundations. Looking south."
Photograph depicts building in wooded area, dirt road and building supplies in foreground. Corresponding note on accompanying photo description page: "3. Service garage. Tarpaper siding."
Photograph depicts two men standing on concrete foundation poured into wood frame in dirt area. Corresponding note on accompanying photo description page: "2. Crib and gravel foundations for oil tanks."
Photograph depicts two long buildings visible behind small wood structure and steel drums. Rough dirt road in foreground, trees and hillside in background. Corresponding note on accompanying photo description page: "4. Prefabs for staff families. Both 48' x 20'. The 96' x 20' prefab is out of the picture to the right."
Photograph depicts one man in front of garage building under construction. Lumber piles cross mid ground, dirt piles in foreground. Corresponding note on accompanying photo description page: "7. Service garage; hoisting up the roof rafters. Lesell in foreground."
Photograph depicts man operating snow plow in dirt area. Trees and mountain peaks visible in background. Corresponding note on accompanying photo description page: "2. Tractor plowing snow off power house site."
Photograph depicts group of men digging trenches in snow, mountains in background. Corresponding note on accompanying photo description page: "9. Digging Mill foundations."
Photograph depicts wood framework (batter boards?) above lines of gravel. Trees and mountain base in background. Corresponding note on accompanying photo description page: "10. Mill foundation trenches - northwest corner."
Photograph depicts men on long building, one on ladder. Rough dirt road in foreground, trees and hillside in background. Corresponding note on accompanying photo description page: "9. 96 x 20 prefab for staff family quarters. Looking south".
Photograph depicts three men digging at mill site, trees and mountainside in background. Corresponding note on accompanying photo description page: "11. Starting to dig mill foundations. Batter boards in background. Looking northeast."
Photograph depicts a long building speculated to be garage behind large snow pile. Truck semi-visible behind snow, another truck partially captured on right. Snowy road in foreground, mountain peaks in background.
Photograph depicts numerous wood buildings in a line, each with a small porch. The cookery, bunkhouse and office are believed to be among the buildings (see 2000.1.1.2.305). Steel drums lie in front of first building, and another building is semi-visible on right, opposite the others. Snowbank in foreground, trees and mountains in background. Photograph taken facing south. See also items 2000.1.1.2.286 and 2000.1.1.2.301
Handwritten annotation in blue ink on recto of photograph: "Portion of Garage interior". Photograph depicts two men standing in rear of garage interior. One car and Eimco loader can be seen in stalls.
Images contain technical engineering drawings from the Asbestos Mining Corp. Drawings are primarily of plant buildings and mining and milling equipment, but also include drafts of town site and utilities, (extensive images of water and sewer pipes and septic systems). Microfiche slides are 4.6cm x 3.5cm mounted on 8.3 x 18.2 cm paper cards with systematic puncture marks, presumed to be an antiquated form of computer memory. Slides are numbered ranging from 1001 to 1549 and a drawing number ranging from 1006 to 8008, generally in the format “2017/02/02”. Microfiche are dated 1950- 1976, several are dated “OLD”, and several are undated. All microfilm reels are annotated “CASSIAR ENGINEERING DRAWINGS”.
Photograph depicts row of houses on either side of street in midground. Forest trees in foreground, mountains in background.
Photograph depicts group of men, women, and children exiting main entrance of building believed to be the school at Cassiar, B.C. Trees and bicycles in foreground.
Photograph depicts what appears to be a Euclid ore haulage truck at entrance of building speculated to be the truck dumping station at crusher plant in mine.
Plant buildings stand in midground. Conveyor believed to be leading to tailings pile can be seen in foreground. Valley and mountains in background.
Photograph depicts large trailer truck parked at what is believed to be the loading station on the Cassiar plant (possibly in mill building).
Photograph depicts two large tanks with Cassiar logo on front, labeled "1" and "2". Road in foreground, garage in background. Mountain base also visible in background.
Photograph depicts a building with a truck parked in front on the corner of Connell Drive and Creery Street.
Photograph depicts four large buildings behind power lines, believed to be located on Malozemoff Avenue. Trucks in foreground, forest and mountains in background.
File contains photographs pertaining to the transportation of asbestos fibre.
- These include portraits of Clinton trailer trucks, trucks from the Cassiar Transport Division at Mile 860 on the Alaskan Highway, the assembly of large freight trucks, an unidentified bridge, and ships and buildings at the Cassiar Shipping Facilities at Pier 94 on the Asbestos Warf in North Vancouver, B.C.
- Twenty-three photographs dated 1982 depict asbestos fiber bales on pallets and inside shipping containers, with accompanying annotations commenting on the quality of the packing. Several images show fibre bales broken during shipment. An accompanying note reads: "SMD - please ensure this cannot reoccur.", and a photo caption reads: "pierced bags are resulting as an environmental problem as fibre is beginning to build up in certain containers." One of the photographs depicting the Cassiar Transport Division was used for promotional posters with the following commentary: "The Cassiar Transport Division operates out of Whitehorse, Yukon Territory and is responsible for delivering the asbestos to the White Pass and Yukon Route terminal in Whitehorse. Fuel oil and supplies are backhauled to the mines. By the end of 1967, the fleet will consist of 65 tractor-trailer units, each of which will carry 23 tons of asbestos. The distance from Whitehorse to Cassiar is 357 miles and Clinton is 403 miles. During the past year, the Division's trucks traveled 2,213,534 miles and handled 75,100 tons, and the mileage to 3.5 million miles. This is a year-round operation and convoys arrive at the mine daily in spite of the long difficult haul. The Division currently employs 43 drivers and 35 mechanics and operates its own maintenance and rebuild facilities in Whitehorse. Over the years these men have established and enviable record of safety, cost and performance."
- Additional photographs that have been integrated depict the Asbestos wharf and its condition, 31 slides of wharf, maps of shipping routes, storage, forklifts, shipping trucks, and packaged asbestos.
- Also included in this file are two copies of a "Photo Survey - Cassiar Ton Units - "Amstelveld & Trojoland" on arrival to Brisbane & Sidney - August 1967." This collection of photographs is a part of an assessment of the efficiency of shipping and transport to Australia from Cassiar. Pictures include: loading, forklifts, storage, ripped bags, broken straps, wharfs, trucks, slings. There are accompanied annotations with each of the photos explaining the safety hazards or inefficiency of the situation. This report was found inside a box linked to James Hardie Industries Ltd. This company is not mentioned in the photograph annotations, but could be related to the report since James Hardie Industries Ltd. was a key player in asbestos mining and manufacturing in Australia.
- Collection of photos of roadside spill of Asbestos, depicting a man with shovel cleaning up on 5 June 1985
- Photos from Eternit Societe Anonyme (a European company that Cassiar shipped to) of packaged Asbestos in storage in 1967
- Collection of photos of James Hardie Coy. Pty. Ltd. shipment of asbestos that was not stored or transported effectively. Many photos depict broken bags as a result of inadequate storage and forklift punctures.
- Collection of photos of Cassiar/Stewart Road Proposal. Photos depict tests of the various stages of shipping and transportation process including forklift tests, Marineo Sling tests, stacking tests, durability tests, container loading tests, problems with current units etc. Also included is a marketing drawing if proposed shipping plan - drawn by "Stewart 1977."
- Photos of shipping process of Turners Asbestos Fibres Lmt. Photos depict lowering asbestos pallets onto barge with swing, and storage on barge.
- Collection of photos of a shipment of asbestos, but the bags of fibre are not identified as a Cassiar shipment therefore the location is unknown.
Photograph depicts group of eight men standing on lawn in front of building known as "House 130" or "Director's Lodge". Left to right: Nick Gritzuk, Charles Rainforth Elliot, W. Harold Connell, Jack Christian, Fred Martin Connell, Ken A. Creery, Plato Malezemoff (from Newmont Mining), Tam Zimmermann. Gritzuk appears to be pointing at photographer. Trees and mountains in background. Most men featured in photo are believed to be members of Cassiar's Board of Directors.
This blueprint depicts the overall layout of the heating and ventilating units to be used for the first and second floor of the recreational centre. Details include the locations of fans, boilers, ducts and exhausts as well as typical heating connector connections and the plumbing layout.
This blueprint depicts the gymnasium lighting layout. Also shown is an isometric view of the air supply unit piping as well as a ventilating unit automatic control diagram. Included are detailed notes regarding system desriptions, its plan and layout as well as directions for the automatic control of the ventilation unit and heating systems.
This blueprint shows the side profile of the proposed tramway at Cassiar. It includes relevant infrastructures and landscape features drawn and marked on the plan such as roads, monocable unloading stations, swamp and beaver ponds as well as streams. The side profile and schematics of the tramway are drawn in parts and includes relevant measurements. Locations of the unloading terminal, jig back towers and jig back loadind stations are included. The overall profile is split into two sections due to elevation changes and lack of drawing surface. Annotation written on the leading edge of the blueprint reads "J.A. Roebling - Proposed Tramway Layout".
Men can be seen working on site, building tools and supplies scattered throughout. Handwritten caption beside this photo reads: "View showing various levels of foundations". A chute of some kind extends from high level to men near bottom. Dirt road at site, and tree-covered valley can be seen in background. Construction of a long structure near the edge of the excavation area can be seen in midground; this is believed to be conveyor "B".
Man in hard hat and overalls bent over wood structure in front of a wood box. Crusher building foundation, mountainside, and power lines in background.
Handwritten caption beside this photo reads: "Work crew eating in open at 10˚ below zero, evicted from Lunchroom, due to damage to, from falling rock." Men are shown sitting in snow. Various metal materials in foreground, snow-covered mountainside in background. It is believed that power lines are also visible in background.
Handwritten caption beside this photo reads: "Placing Crusher Pinion; Pitman; weight approx. 20 tons". Man stands on top of a very tall, red peice of equipment believed to be a crusher pitman. Boom of crane is visible in foreground, and two other men stand on a high level of the crusher building. Crusher foundations, an unidentified building, and mountain in background.
Handwritten caption beside this photo reads: "Erection of steel framework of Building". Red rectangular equipment stands enclosed in wood frame, which is also being enclosed in the much larger steel frame of the crusher building. Men are working on site, and boom of traveler crane can be seen on right. Other buildings at crusher plant are visible at top of mountain in background.
Handwritten caption beside this photo reads: "View of Bin and Pan Feeder". Interior view of crusher building. A square, snow-covered object is being lowered by crane into building.
Photograph depicts two similar wood structures built into mountainside in snowy area. Unidentified machinery in foreground on far left. Power lines or other cables above in background.
Photograph depicts the steel sheeting of the crusher building underway. Three men stand on platform suspended by cables close to roof of crusher building. Three other men can be seen working on the roof of the building, one walking, one sitting, one lying on his stomach very close to the edge. All are wearing safety gear. Cassiar mountain range in background.
Handwritten caption beside this photo reads: "Conveyor 'B' from below, & Propane Tank." Conveyor sits on tall steel framework and encased in steel sheeting, elevated over gravel area and propane tank. Conveyor structure stands to right of snow-covered slope. It is believed that the crusher building stands in background.
Unidentified wood structures in foreground on far left.
Conveyor sits on tall steel framework, encased in steel sheeting, and stands to right of snow-covered slope. Propane tank sits on log structure below conveyor. Snowy mountains in background. See also item 2000.1.1.2.373. Handwritten caption below this photo reads: "Project completed - at 52˚ temp."