View of trench for 8" dia. E.S. from camp at about E 31+00 Approx. 200' of trench in 3 hrs. (3:30 p.m.)
Looking N. along 3" dia. W.P. line W. of M.R. excavation.
View from S. of gate on chip truck road looking S. along new camp access road.
North chip conveyor bent support.
West leg, North bent of chip conveyor looking S.E.
Chip dumper - looking N.
Looking along trench from camp ES #5 MH to Lift Station.
Spirogester tank, looking S.
Pulping Group excavation - looking N.
From roof of Digester - looking S.W.
30" EAS 36-003 under existing 30" EC
12" EA line from Recaust Pump House into existing 36" EA Wood Stave Line.
36" WMC-36-144 in trench looking SE.
Stockpiling pit run from SE corner of old gravel pit looking NE.
14" FRP EA line connection into MH#.
36" VMC-36-140 excavation at N63 + 45 looking NW.
Track supports over 30" EC-36-040 & 30 EM-36-060 looking NW.
36" WMC-36-140 looking SE from N63 + 75.
Looking NE from top of pit run stockpile.
Pit run & 3/4" minus stock piles looking NE. Pile driving rig for W. bridge at R.
WFP tie-in at N53 + 47 x E49 + 90 looking East.
Influent and effluent boxes for Spirogester.
Looking NW across M.R. excavation from E. end of walkway. First day of work.
Pulp. Gp. excavation from point near SW corner existing Pulp. Gp. looking SE.
Pulp. Gp. excavation from point E. of conveyor bent #2 and N. of road look. NW.
Spoiled. [pipe laid in a ditch]
View from NW corner of walkway into 3" dia. W.P. excavation (machine room)
Excavation for 3" dia. W.P. line from NW corner of walkway looking N.
Le Tourneau moving logs.
Propane vapourizer station - East side Power Group.
Putting in thrust block form 3" WP line West of M.R.
Broken electrical cables in Power Group excavation.
Looking S.W. into Power Group excavation.
First 60' section of 42" F.R.P. EAS pipe in place.
Support pile for power pole at West side of south bent of chip conveyor.
M.R. backfilling - looking North.
Chip car unloader - looking S.S.W.
Scenic shots from road to Mill
Scenic shots from road to Mill
North bent chip conveyor - looking N.
36" WMC trench at 15" EA break.
From Digester tower - looking S.E.
From roof of Digester - looking N.
From roof of Digester - looking N.