Lime rock track pit from top of lime rock pile looking NE.
Fndn. excavation for "B" mill evaporator from N. end looking S.
N. end of "B" mill Pulp Gr. from roof of "A" mill digester looking S.
400 A temporary power panel 575V.
N. end of "B" mill Pulping Gr. from roof of chemical unloading shed looking W.
NW. corner of "B" mill Pulping Gr. from roof of "A" mill looking SW.
SW. corner of "B" mill Pulping Gr. from roof of 33rd floor Pulping Gr. looking SW.
Lime kiln precipitator fndn. looking NE.
"B" mill Power Gr. from track #14 looking NW.
EAS neutralization tank from N. end looking S.
Foundation excavation black liquor tank in foreground, "B" mill evaporator bldg. in background from warehouse roof looking S.
Foundation excavation for recaust bldg. extension from roof of caustic tower #50 looking SE.
"A" mill machine room from roof of #2 blow tank looking N.
Foundation excavation for recaust bldg. extension.
Trench for rerouted bunker coil liner etc. from S. end looking N.
"B" mill recovery boiler foundations from stairs on E. wall of "A" mill, power boiler bldg. looking NE.
New lime kiln fndn. excavation from N. end looking SW.
Footing for coal MXA-53 looking SE.
Excavation for recaust bldg. extension from N. side looking S.
Excavation at N. end of old lime kiln bldg. from E. side looking W.
Lime rock conveyor from track #14 looking NW.
Demolished retaining wall at Pulping Gr. front chute W. end looking E.
Tank fndn slab along E. wall of "B" mill Pulping Gr. from S. end looking NE.
Lime kiln precipitator fndn. from SW corner looking NE.
SE. corner of "A" mill Power Gr. bldg. from SE corner of "B" mill Power Gr. looking NW.
Rerouted oil lines at NE. corner of salt cake unloading shed looking NW.
Looking NW along new warehouse addition from roof at NE sorner of "A" mill machine room.
Unloading glulam beams for warehouse addition roof.
Applying insulation to existing B.L. tanks from roof of shops looking E.
"B" machine room from roof of bleached H.D. tank looking N.
"14" EAS-36-005 line from weak B.L. tank looking SW.
Trench for "14" EAS-36-005 and at N. side of "A" mill evaps. looking E.
N. end of fuel oil heater bldg. from "B: mill fndn. excavation looking SW.
"B" mill Power Gr. from walkway at SE corner of "A" mill Power Gr. bldg. looking NE.
Soap tanks fndn. excavation from SE. corner looking NW.
"B" mill machine rm. from roof of "A" digester looking N.
Lime rock stockpile track pit and lime kiln precipitor fndn. from roof of "A" mill digester looking SE.
S. end of "B" mill Pulping Gr. from roof of chemical unloading shed looking SW.
SW. corner of "B" mill Pulping Gr. from roof of 3rd floor Pulping Gr. looking S.
No. 2 turbo generator building excavation from roof of #50 caustic tower looking E.
N. end of "B" mill machine rm. from roof of "A" mill machine rm. looking NW.
"B" mill machine rm. broke pit from roof of "A" mill machine rm. looking W.
"B" mill Power Gr. from SE. corner of "A" mill Power Gr. building looking NE.
Hydrant riser of 10" WFP-36-127 at N55 + 85.5 and E31 + 36.
Half way plus, during 1200 cubic yards poured for brown stock and bleached H.D. tanks fndn slab S. end looking NE.
"B" mill recovery boiler precipitator foundation excavation from near track #14 looking NW.
Excavation for foundation for new liquor spill collecting tank from NE corner looking SW.
Applying insulation on existing weak B.L. tank.
Lime rock track pit from W. end looking E.
Pouring fndn for tanks along E. wall of "B" mill Pulping Gr. from S. end looking N.