Several new buildings, such as the digester tower and the hi-density storage tanks, are constructed during the pulpmill expansion.
A helicopter attaches a pipe to the side of the digester.
An aerial of Northwood Pulp Mill during the expansion.
An aerial of Northwood Pulp Mill during the expansion with the digester towers in the background and the mill complex in the foreground.
"B" Mill Machine Room, south side of wire silo showing position of fan pump suction.
"B" Mill Turbo-Generator inner skin cladding N.S. central rd. looking N.
Excavation E.W. corridor MH3B, IF, 10" GF MH, 24" EMC 36-061 4" ES 36-083 2 valves on 6" WFP 36-130, 1 gas riser on 6" GF 36-207 and gas riser on 8" GF 36-207 looking S.E.
"B" Mill Excavation 23"ULD 36-240 and 241, 12" EA 36-009 central N.S. rd. looking S.E.
Excavation E.W. corridor power-recaust 4"ES, 24" EMC-36-061 MH3B, Gas 10"GF MH.
Excavation E.W. corridor power-recaust 4"ES, 24" EMC-36-061 MH3B, Gas 10"GF West.
"B" Mill digester. Kamyr/Horton vertomatic welder.
E.W. corridor between power and recaust showing 24"EMUC & 10"GF, looking N.E.
"B" Mill Recovery Bldg. lifting 1st economizer tube bundles to correct elevators looking west.
Recaust - Piping between W.L.S. Tank and #3 L.M.W. Tank looking N.W.
Insulate 1/2" 0 steam trace line existing from 4" 0 mud line going to 30" 0 EAS line from "A" mill pulp. grp. looking N.W.
"B" Mill Pulping Group lifting section of Caustic Tower #20 in place looking N.
"B" Mill Pulping Group temporary digester Tower hoist block looking N.E.
"B" Mill Machine Room steel beam bracket at column MA X 56.
"B" Mill Machine Room Temporary Steam Heaters at Column MXA X 62 looking S.E.
"B" Mill Pulping Group temporary Digester Tower hoist looking N.W.
Rebuilt foam tower looking S.E.
"A" Mill Machine Room roof looking S. along E. wall.
"B" Mill Power Group. Trench formwork along E. wall of "A" Mill Power Group looking N.W.
"B" Mill Pulping Group Bleach Towers #10 and #20 from Track #9 looking N.W.
Foundation for utility bridge tower #5 looking S.E.
Gravel stock pile from W. end looking S.E.
"B" Mill Pulping Group, Digester Tower, N. wall looking S.
"B" Mill Pulping Group Digester cladding W. wall from N.W. road looking E.
No. 2 Rail Car Chip Dumper Tunnel excavation looking N.E.
"A" Mill Bleached Stock Spill near "B" Mill Machine Room Reactor Pit looking S.E.
Heating registers thru W. wall "A" Mill Machine Room into "B" Mill Machine Room looking S.E.
Heating registers thru W. wall "A" Mill Machine Room into "B" Mill Machine Room looking S.E.
"B" Mill Machine Room, S. wall looking N.E.
No. 2 Rail Car Chip Dumper Tunnel excavation looking.
No. 2 Rail Car Chip Dumper abandoned blow line sections looking N.E.
No. 2 Rail Car Chip Dumper Tunnel Excavation looking N.W.
No. 2 Rail Car Chip Dumper Tunnel Excavation looking N.E.
No. 2 Rail Car Chip Dumper Tunnel Excavation looking N.
No. 2 Rail Car Chip Dumper Tunnel Excavation looking S.
"B" Mill Machine Room looking N.W.
"B" Mill Machine Room Sample Storage Room looking S.W.
"B" Mill Pulping Group. 13'-6X26'-0 Bleached stock vacuum washer drum.
"B" Mill Pulping Group. Impco single shaft steam mixers.
"B" Mill Power Group looking S.W.
"B" Mill Pulping Group looking N.E.
Water Treatment Clarifier looking S.E.
"B" Mill Power Group from Track #14 looking N.
"B" Mill Power Group E. Wall looking N.W.
"B" Mill Power Group looking N.W.
Lime Kiln Piers from track #14 looking N.W.