Water Treatment Clarifier from N. side of Water Treatment Plant looking N.
Looking E. down South dike from aoubt TP19.
Spoil area at worked out gravel pit looking S.E.
Water boiling up at about N. and E.
Tert pit along south dyke looking N.
24" EMUC-36-062 outlet from Fiber Salvage Sump looking E.
Fiber Salvage Sump looking N.E.
"B" Mill Machine Room, south side of wire silo showing position of fan pump suction.
"B" Mill Turbo-Generator inner skin cladding N.S. central rd. looking N.
Excavation E.W. corridor MH3B, IF, 10" GF MH, 24" EMC 36-061 4" ES 36-083 2 valves on 6" WFP 36-130, 1 gas riser on 6" GF 36-207 and gas riser on 8" GF 36-207 looking S.E.
"B" Mill Excavation 23"ULD 36-240 and 241, 12" EA 36-009 central N.S. rd. looking S.E.
Excavation E.W. corridor power-recaust 4"ES, 24" EMC-36-061 MH3B, Gas 10"GF MH.
Excavation E.W. corridor power-recaust 4"ES, 24" EMC-36-061 MH3B, Gas 10"GF West.
"B" Mill digester. Kamyr/Horton vertomatic welder.
E.W. corridor between power and recaust showing 24"EMUC & 10"GF, looking N.E.
"B" Mill Recovery Bldg. lifting 1st economizer tube bundles to correct elevators looking west.
Recaust - Piping between W.L.S. Tank and #3 L.M.W. Tank looking N.W.
Insulate 1/2" 0 steam trace line existing from 4" 0 mud line going to 30" 0 EAS line from "A" mill pulp. grp. looking N.W.
"B" Mill Pulping Group lifting section of Caustic Tower #20 in place looking N.
"B" Mill Pulping Group temporary digester Tower hoist block looking N.E.
"B" Mill Machine Room steel beam bracket at column MA X 56.
"B" Mill Machine Room Temporary Steam Heaters at Column MXA X 62 looking S.E.
"B" Mill Pulping Group temporary Digester Tower hoist looking N.W.
Rebuilt foam tower looking S.E.
"A" Mill Machine Room roof looking S. along E. wall.
"B" Mill Power Group. Trench formwork along E. wall of "A" Mill Power Group looking N.W.
"B" Mill Pulping Group Bleach Towers #10 and #20 from Track #9 looking N.W.
Foundation for utility bridge tower #5 looking S.E.
Gravel stock pile from W. end looking S.E.
"B" Mill Pulping Group, Digester Tower, N. wall looking S.
"B" Mill Pulping Group Digester cladding W. wall from N.W. road looking E.
Looking along trench from camp ES #5 MH to Lift Station.
Spirogester tank, looking S.
Pulping Group excavation - looking N.
From roof of Digester - looking S.W.
30" EAS 36-003 under existing 30" EC
12" EA line from Recaust Pump House into existing 36" EA Wood Stave Line.
36" WMC-36-144 in trench looking SE.
Stockpiling pit run from SE corner of old gravel pit looking NE.
14" FRP EA line connection into MH#.
36" VMC-36-140 excavation at N63 + 45 looking NW.
Track supports over 30" EC-36-040 & 30 EM-36-060 looking NW.
36" WMC-36-140 looking SE from N63 + 75.
Looking NE from top of pit run stockpile.
Pit run & 3/4" minus stock piles looking NE. Pile driving rig for W. bridge at R.
WFP tie-in at N53 + 47 x E49 + 90 looking East.
Influent and effluent boxes for Spirogester.
30" EM-30-060 & 30" EC-36-060 at track supports for Track 9 looking North.
See drawing attached [rail cars]
See drawing attached [railroad tracks]