Trench for 15KV 250MCM cable to water treatment plant E. end looking W.
EAS neutralization tank access manhole looking SE.
S. end of "B" mill machine room from near N. end looking SE.
Footings & pedestals for enclosure for lead end, lime rock conveyor looking SW.
Broke pit area, "B" mill machine room from roof of "A" mill machine room looking W.
"B" mill Pulping Group from roof of recaust building looking W.
CLO2 & NaOH seal pit foundation at PBI-32P looking W.
Trench for relocated air, water, and electrical lines between filter building and chip blower building looking NE.
Track #6A from N67+25 looking N.
Trench for rerouted air, water & electrical lines between filter building and chip blower building at W. end of lime rock ramp looking SE.
N. end of "B" mill Power Group from platform on E. wall of "A" mill Power Group looking N.
"B" mill Pulping Group N. end from roof of chemical unloading shed looking W. (8:00 a.m.)
"B" mill Power Group N. end from platform on e. wall of "A" mill Power Group looking N. (8:14 a.m.)
New lime kiln foundation S. end from roof of existing lime kiln building looking S.
Warehouse addition roof from roof of "A" mill machine room looking N.
"B" mill machine room from roof of "A" mill bleached H.D. tower looking N.
MCC 14-4 E. face N. side.
"A" mill power group, E. wall from hog conveyor tower looking W.
Foundation forms for "B" mill blending tank and broke tank looking NW.
N. end of walkway on E. wall of "A" mill Power Group floor E1 1932.5 at Col. RF47 looking N.
Doorway on S. side of "A" mill Power Group just W. of Col. RF45 floor E1 1916.5 looking N.
First steel "B" mill Pulping Group Col. PA2-38P from E. wall looking W.
24" WMC-36-142, 30" EMUC-36-060 & 30' EC-36-040 at about E35+50 looking NE.
Track #5A from N 66+75 looking N.
"B" mill Power Group from NE corner looking SW.
Warehouse addition from "A" mill machine roof looking N.
"B" mill Pulping Group from E. side looking W.
Excavation for M.H. 1D looking N.
30" EC-36-040 at S. end of "B" mill Pulping Group looking NE.
Leak in 36" EAW line at N61+75 looking W.
24" WMC-36-142, 30" EC-36-040 at about E 35+50 looking NE.
"B" mill Pulping Group N. end from roof of chemical unloading shed looking W.
"B" mill Power Group from near hog conveyor tower looking W.
"B" mill machine room from roof of existing blending tank looking N.
"B" mill Pulping Group from stairs on S. wall of "A" mill Pulping Group looking S.
Track #14 from about N62+50 looking N.
24" EMUC-36-062 at "A" mill machine room wall looking N.
Foundations for "B" mill blending and broke tanks looking NW.
24" WMC-36-142, 30" EC-36-040 & 30" EMUC-36-060 at about E35+50 looking NW.
Excavation for 60" chip conveyor along W. side of chip silos looking S.
"B" mill recovery boiler support column.
1800 gal. propane tank in new location on N. side of fuel oil day tank looking SE.
SE. corner of "B" mill machine room from top of "A" mill blending tank looking N.
Excavation for utility bridge foundation B2 looking E.
Warehouse addition NE. corner looking E.
Backfilled trench for 24" EMUC-36-062 in "A" mill bleach plant looking W.
6" WFP relocation at SE. corner of "A" mill power group looking SW.
Track #14 from SE. corner of "B" mill power group looking NE.
"B" pulping group from NW. corner looking SE.
Canrons 165 ton crawler crane.