Utility bridge bents #T1 & #T2 from top of "A" mill digester looking N.
"B" mill machine room from top of "A" mill digester looking N.
View of new bridge approach from top of "A" mill digester looking E.
View of new bridge approach from top of "A" mill digester looking E.
42" EAS-36-001 joint at mis-match of 0's after partial layings N. side.
42" EAS-36-001 joint showing mis-match of 0's after partial layings S. side.
42" EAS-36-001 joint showing mis-match of 0's looking upstream.
42" EAS-36-001 joint showing mis-match of 0's at 38+90 looking upstream.
"B" mill pulping group from roof of chemical unloading shed looking NW.
Canrons 165 ton crawler crane.
H.A.S. field office A/C system looking NW.
"B" pulping group from NW. corner looking SE.
H.A.S. field office looking NW.
Chip truck dump hopper excavation from NE. corner looking SW.
Truck for 42" EAS-36-001 at S. limit of contract C401 looking NE.
Track #14 from SE. corner of "B" mill power group looking NE.
6" WFP relocation at SE. corner of "A" mill power group looking SW.
Recaust building addition excavation from roof of #1 turbo-generator building looking SW.
Foundations fof #2 turbo-generator building from roof of #1 turbo-generator building looking NW.
Warehouse addition from NW. corner looking SE.
Warehouse addition NE. corner looking E.
"B" mill blending tank & broke tank foundation looking E.
Excavation for utility bridge foundation B2 looking E.
"B" mill pulping group from roof of chemical unloading shed looking W.
Putrescible dump from SW. bank looking N.
"B" mill pulping group from stairs on S. side of "A" mill pulping group looking S.
1800 gal. propane tank in new location on N. side of fuel oil day tank looking SE.
42" EAS-36-001 at S. limit of contract 401 looking N.
8" WFP tie-in at N64+275 on W. side of "A" mill machine room looking SE.
"B" mill power group from roof of salt cake unloading building looking SW.
M.H. 2D and 12" EMUC-36-066 from in front of pump house looking E.
30" EMUC-36-060 & 30" EC-36-040 from about E35+50 looking W.
Petrescible dump pit W. side looking E.
Tracks #17 & #18 from N. wall of warehouse addition looking N.
Warehouse addition W. wall from N. end looking S.
Excavation for black liquor storage tanks looking SE.
Warehouse addition roof from "A" mill machine room roof looking NW.
"B" mill recovery boiler support column.
"B" mill Power Group from SE. corner of salt cake unloading building looking SW.
Lime kiln foundations from top of lime rock bucket elevator looking N.
Excavation for 60" chip conveyor along W. side of chip silos looking NW.
"A" mill Power Group E. wall at column RF-47 from inside looking NE.
"A" mill Power Group E. wall at column RF-47 ;pplomg NW.
"B" mill Pulping Group from roof of filter building looking N.
Lime rock track pit from roof of filter building looking SE.
Opening in lime rock conveyor wall looking SE.
Tracks 9, 9A & 9B from about N61+75 looking SW.
Excavation for 60" chip conveyor along W. side of chip silos looking S.
Warehouse addition from near hydrant #4 looking SE.
"B" mill machine room from enar sub-station looking SE.